During the project management process, an organization develops a document that details preferred and authorized interactions among project team members, senior management, and other project stakeholders. Which of the following types of documents were developed?

Options

  • AQuality management plan
  • BChange control plan
  • CCommunications management plan
  • DRisk management plan