nerdexam
CompTIA

PK0-003 · Question #55

During the project management process, an organization develops a document that details preferred and authorized interactions among project team members, senior management, and other project stakehold

The correct answer is C. Communications management plan. A communications management plan details the preferred and authorized interactions among all project stakeholders.

Tools and documentation

Question

During the project management process, an organization develops a document that details preferred and authorized interactions among project team members, senior management, and other project stakeholders. Which of the following types of documents were developed?

Options

  • AQuality management plan
  • BChange control plan
  • CCommunications management plan
  • DRisk management plan

How the community answered

(60 responses)
  • A
    7% (4)
  • B
    2% (1)
  • C
    88% (53)
  • D
    3% (2)

Why each option

A communications management plan details the preferred and authorized interactions among all project stakeholders.

AQuality management plan

A quality management plan focuses on how quality standards will be met throughout the project.

BChange control plan

A change control plan describes the process for managing changes to project baselines.

CCommunications management planCorrect

A communications management plan defines the structure for information flow, detailing who is responsible for communicating, what information needs to be shared, when and how often communication should occur, and to whom it should be directed. This ensures effective and authorized interactions among all project stakeholders.

DRisk management plan

A risk management plan outlines how project risks will be identified, analyzed, and responded to.

Concept tested: Project communications management plan

Topics

#Communications management plan#Stakeholder communication#Project planning

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice