Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?

The correct answer is B. Activity A must end before Activity B can begin.. A 'finish-to-start' relationship dictates that the predecessor activity must be completed before the successor activity can commence.

Project life cycle phases

Question

Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?

Options

  • AActivity A must end before Activity B can end.
  • BActivity A must end before Activity B can begin.
  • CActivity A must begin before Activity B can begin.
  • DActivity A must begin before Activity B can end.

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    91% (43)
  • C
    2% (1)
  • D
    4% (2)

Why each option

A 'finish-to-start' relationship dictates that the predecessor activity must be completed before the successor activity can commence.

AActivity A must end before Activity B can end.

This describes a finish-to-finish (FF) relationship, where Activity A must end before Activity B can end.

BActivity A must end before Activity B can begin.Correct

In a finish-to-start (FS) relationship, the predecessor activity (Activity A) must be 100% complete before the successor activity (Activity B) can start. This is the most common type of logical relationship in project scheduling, ensuring sequential execution of tasks.

CActivity A must begin before Activity B can begin.

This describes a start-to-start (SS) relationship, where Activity A must begin before Activity B can begin.

DActivity A must begin before Activity B can end.

This describes a start-to-finish (SF) relationship, which means Activity A must begin before Activity B can finish.

Concept tested: Project schedule activity relationships

Topics

#Project scheduling#Activity dependencies#Finish-to-start