PK0-003 · Question #54
Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?
The correct answer is B. Activity A must end before Activity B can begin.. A 'finish-to-start' relationship dictates that the predecessor activity must be completed before the successor activity can commence.
Question
Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?
Options
- AActivity A must end before Activity B can end.
- BActivity A must end before Activity B can begin.
- CActivity A must begin before Activity B can begin.
- DActivity A must begin before Activity B can end.
How the community answered
(47 responses)- A2% (1)
- B91% (43)
- C2% (1)
- D4% (2)
Why each option
A 'finish-to-start' relationship dictates that the predecessor activity must be completed before the successor activity can commence.
This describes a finish-to-finish (FF) relationship, where Activity A must end before Activity B can end.
In a finish-to-start (FS) relationship, the predecessor activity (Activity A) must be 100% complete before the successor activity (Activity B) can start. This is the most common type of logical relationship in project scheduling, ensuring sequential execution of tasks.
This describes a start-to-start (SS) relationship, where Activity A must begin before Activity B can begin.
This describes a start-to-finish (SF) relationship, which means Activity A must begin before Activity B can finish.
Concept tested: Project schedule activity relationships