PK0-003 · Question #53

Which of the following is crucial to scope management?

The correct answer is D. A formal change management process. A formal change management process is essential for scope management, as it controls and approves all modifications to the project's scope baseline.

Project management concepts

Question

Which of the following is crucial to scope management?

Options

  • AA Work Breakdown Structure dictionary
  • BA final statement of project objectives
  • CAn automated scope management system
  • DA formal change management process

How the community answered

(20 responses)
  • A
    5% (1)
  • D
    95% (19)

Why each option

A formal change management process is essential for scope management, as it controls and approves all modifications to the project's scope baseline.

AA Work Breakdown Structure dictionary

A Work Breakdown Structure dictionary defines the deliverables and activities within the WBS but does not inherently manage changes to the scope itself.

BA final statement of project objectives

A final statement of project objectives defines what the project aims to achieve but doesn't provide a mechanism for managing changes to the scope after it's defined.

CAn automated scope management system

An automated scope management system might facilitate the process but the underlying formal process, not the automation itself, is the crucial element.

DA formal change management processCorrect

A formal change management process is crucial for scope management because it provides a structured way to review, approve, or reject changes to the project scope baseline, preventing scope creep and ensuring that only authorized modifications occur. This process ensures that all changes are documented and their impact assessed before implementation.

Concept tested: Project scope change management process

Topics

#Scope management#Change management#Scope control