PK0-003 · Question #433
Which of the following would MOST likely contain warranty information for the project deliverable?
The correct answer is D. Transition plan. Warranty information for project deliverables is typically included in the transition plan, which outlines how the project's output will be handed over and supported post-completion.
Question
Which of the following would MOST likely contain warranty information for the project deliverable?
Options
- AScope statement
- BCost baseline
- CRisk assessment
- DTransition plan
How the community answered
(63 responses)- A3% (2)
- B2% (1)
- C2% (1)
- D94% (59)
Why each option
Warranty information for project deliverables is typically included in the transition plan, which outlines how the project's output will be handed over and supported post-completion.
A scope statement defines what is and is not included in the project, not post-delivery warranty details.
A cost baseline is a time-phased budget, used for cost control, not for warranty information.
A risk assessment identifies and analyzes potential risks to the project, not post-delivery support or warranty terms.
The transition plan details how the project's deliverables will be moved from the project team to operational support, including aspects like training, support, and contractual obligations such as warranties. It ensures a smooth handover and specifies post-project responsibilities for the deliverable.
Concept tested: Project transition planning and deliverables