PK0-003 · Question #433

Which of the following would MOST likely contain warranty information for the project deliverable?

The correct answer is D. Transition plan. Warranty information for project deliverables is typically included in the transition plan, which outlines how the project's output will be handed over and supported post-completion.

Tools and documentation

Question

Which of the following would MOST likely contain warranty information for the project deliverable?

Options

  • AScope statement
  • BCost baseline
  • CRisk assessment
  • DTransition plan

How the community answered

(63 responses)
  • A
    3% (2)
  • B
    2% (1)
  • C
    2% (1)
  • D
    94% (59)

Why each option

Warranty information for project deliverables is typically included in the transition plan, which outlines how the project's output will be handed over and supported post-completion.

AScope statement

A scope statement defines what is and is not included in the project, not post-delivery warranty details.

BCost baseline

A cost baseline is a time-phased budget, used for cost control, not for warranty information.

CRisk assessment

A risk assessment identifies and analyzes potential risks to the project, not post-delivery support or warranty terms.

DTransition planCorrect

The transition plan details how the project's deliverables will be moved from the project team to operational support, including aspects like training, support, and contractual obligations such as warranties. It ensures a smooth handover and specifies post-project responsibilities for the deliverable.

Concept tested: Project transition planning and deliverables

Topics

#Transition plan#Project deliverables#Warranty

Community Discussion

No community discussion yet for this question.