nerdexam
CompTIA

PK0-003 · Question #434

Before the execution phase begins, who is in control of the project?

The correct answer is C. Project manager. Before project execution, the Project Manager is responsible for all planning activities, thus having control over the project's direction and strategy.

Project life cycle phases

Question

Before the execution phase begins, who is in control of the project?

Options

  • AProject sponsor
  • BProgram manager
  • CProject manager
  • DProject coordinator

How the community answered

(28 responses)
  • A
    4% (1)
  • C
    96% (27)

Why each option

Before project execution, the Project Manager is responsible for all planning activities, thus having control over the project's direction and strategy.

AProject sponsor

The project sponsor provides resources and high-level support but is not directly in control of the day-to-day project planning or execution details.

BProgram manager

A program manager oversees multiple related projects, not typically having direct control over a single project's pre-execution phase.

CProject managerCorrect

The Project Manager is accountable for planning, executing, and closing the project, and thus maintains control of the project's overall direction and management from initiation through planning and before execution begins. During the planning phase, the Project Manager leads the development of the project plan, defining scope, schedule, budget, and resources.

DProject coordinator

A project coordinator assists the project manager with administrative tasks but does not have ultimate control over the project.

Concept tested: Project manager responsibilities and project phases

Source: https://learn.microsoft.com/en-us/training/modules/project-management-introduction/4-project-manager

Topics

#Project manager responsibilities#Project phases#Project control

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice