PK0-003 · Question #295

Which of the following would be included in the project transition plan?

The correct answer is C. Maintenance responsibilities of the project deliverables.. A project transition plan outlines how the project's deliverables will be handed over to operations and sustained by the organization after project completion.

Tools and documentation

Question

Which of the following would be included in the project transition plan?

Options

  • ASpecifications used for quality control measurements.
  • BComparison of project deliverables with organizational strategic goals.
  • CMaintenance responsibilities of the project deliverables.
  • DAnalysis of the project expenditures.

How the community answered

(37 responses)
  • B
    3% (1)
  • C
    95% (35)
  • D
    3% (1)

Why each option

A project transition plan outlines how the project's deliverables will be handed over to operations and sustained by the organization after project completion.

ASpecifications used for quality control measurements.

A is incorrect because specifications used for quality control measurements are typically part of the quality management plan, not the transition plan.

BComparison of project deliverables with organizational strategic goals.

B is incorrect because comparing project deliverables with organizational strategic goals is part of project planning and ongoing monitoring, particularly during project closure, but not the primary focus of a transition plan.

CMaintenance responsibilities of the project deliverables.Correct

C is correct because the project transition plan explicitly defines how the project's outputs (deliverables) will be integrated into ongoing operations and who will be responsible for their long-term upkeep and support. This includes maintenance, support, and operational responsibilities to ensure the successful long-term viability of the project's results, thereby ensuring the organization can effectively utilize the project's outcome.

DAnalysis of the project expenditures.

D is incorrect because analysis of project expenditures is part of financial management and project closure reporting, rather than the operational handover focus of a transition plan.

Concept tested: Project transition plan components

Source: https://www.projectmanager.com/blog/project-transition-plan

Topics

#project transition plan#maintenance responsibilities#operational handover