PK0-003 · Question #290
A project scope document should include which of the following items? (Select TWO).
The correct answer is C. Key performance indicators D. Detailed objectives. A project scope document clearly defines what the project aims to achieve and how its success will be measured, incorporating detailed objectives and key performance indicators.
Question
A project scope document should include which of the following items? (Select TWO).
Options
- ACost control
- BContinuous service improvements
- CKey performance indicators
- DDetailed objectives
- ERisk management plan
How the community answered
(43 responses)- A5% (2)
- B7% (3)
- C86% (37)
- E2% (1)
Why each option
A project scope document clearly defines what the project aims to achieve and how its success will be measured, incorporating detailed objectives and key performance indicators.
Cost control is a part of project management and financial planning, not a defining element of the project scope itself.
Continuous service improvement is an operational methodology, typically post-project or for ongoing services, rather than a direct component of a specific project's scope definition.
Key performance indicators (KPIs) are crucial for measuring project success and are therefore an essential component of a project's scope, defining what success looks like.
Detailed objectives clearly define what the project aims to achieve and are fundamental to establishing the boundaries and deliverables of the project scope.
A risk management plan is a separate project management plan, dealing with identifying and responding to risks, not defining the fundamental boundaries of what the project will deliver.
Concept tested: Components of a project scope document
Source: https://www.pmi.org/learning/library/scope-statement-project-success-6771