There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

The correct answer is A. Accept it. When a resource risk has a high probability but a low impact, the most appropriate response is to accept it, as the potential consequences do not justify expending resources to prevent or mitigate it.

Project management concepts

Question

There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

Options

  • AAccept it
  • BAvoid it
  • CMinimize it
  • DMitigate it

How the community answered

(34 responses)
  • A
    85% (29)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Why each option

When a resource risk has a high probability but a low impact, the most appropriate response is to accept it, as the potential consequences do not justify expending resources to prevent or mitigate it.

AAccept itCorrect

When the impact of a risk is determined to be low, the most practical response is often to accept it. Accepting a risk means no specific action is taken to address it, as the potential consequences do not warrant expending resources for avoidance or mitigation.

BAvoid it

Avoiding a risk usually means eliminating its cause, which is done for high-impact or high-probability risks, not typically for low-impact ones.

CMinimize it

Minimizing a risk involves reducing its probability or impact, which is generally done when the risk is deemed significant enough to warrant intervention.

DMitigate it

Mitigating a risk means reducing its impact or probability, a response usually reserved for risks with a higher impact or a more critical nature.

Concept tested: Risk response strategies for low impact

Source: https://www.pmi.org/learning/library/project-risk-management-process-6997

Topics

#risk management#risk response strategies#risk acceptance