nerdexam
CompTIA

PK0-003 · Question #199

A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:

The correct answer is A. Arisk register.. The project is experiencing problems due to unpredicted and unplanned uncertain events.

Tools and documentation

Question

A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:

Options

  • AArisk register.
  • BChange management.
  • CAn issues log.
  • DAcommunication plan.

How the community answered

(16 responses)
  • A
    88% (14)
  • B
    6% (1)
  • D
    6% (1)

Why each option

The project is experiencing problems due to unpredicted and unplanned uncertain events.

AArisk register.Correct

A risk register is a document that tracks identified risks, their potential impact, likelihood, and planned mitigation or contingency responses for uncertain events that may affect the project. By using a risk register, these uncertain events would have been identified, tracked, and planned for, allowing the team to address them proactively.

BChange management.

Change management controls modifications to the project, not the identification and planning for uncertain future events.

CAn issues log.

An issues log tracks problems that have already materialized, it does not proactively track uncertain future events.

DAcommunication plan.

A communication plan focuses on information dissemination, not on identifying and planning for potential uncertain future events.

Concept tested: Project risk management

Topics

#Risk management#Risk register#Uncertainty

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice