A network diagram is used to organize which of the following?
The correct answer is A. Critical path. A network diagram visually represents project activities and their dependencies, which is fundamental for identifying the critical path.
Question
A network diagram is used to organize which of the following?
Options
- ACritical path
- BDefects
- CWBS
- DIssues
How the community answered
(41 responses)- A85% (35)
- B2% (1)
- C5% (2)
- D7% (3)
Why each option
A network diagram visually represents project activities and their dependencies, which is fundamental for identifying the critical path.
A network diagram illustrates the sequence of project activities and their logical relationships, allowing for the calculation of activity durations and identification of the longest sequence of dependent activities, known as the critical path. The critical path represents the earliest a project can be completed, making it a primary output derived from the diagram.
Defects are quality management outputs and are not typically organized or directly identified by a project network diagram.
A Work Breakdown Structure (WBS) decomposes project deliverables into smaller, manageable components, but it is not organized by a network diagram; rather, the WBS typically precedes the creation of activities for a network diagram.
Issues are problems encountered during a project that require resolution and are tracked in an issue log, not organized by a network diagram.
Concept tested: Project network diagram purpose