nerdexam
ExamsPK0-003Questions#169
CompTIA

PK0-003 · Question #169

PK0-003 Question #169: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-003 to reveal the answer and full explanation for question #169. The question stem and answer options stay visible for context.

Question

A project has two resources scheduled to work 40 hours a week for four weeks, both at $85.00 an hour. One resource called in sick for 16 hours, while the other resource worked four hours additional. Which of the following is the cost of the resources?

Options

  • A$25,840
  • B$26,180
  • C$27,200
  • D$27,540

Unlock PK0-003 to see the answer

You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-003 Practice