The correct answer is B: Resource A to confirm estimates.. See the full explanation below for the reasoning.

Question

A project has been going on for three weeks, and the project manager notices that Resource A is beginning to fall behind schedule. The project manager should FIRST schedule a meeting with:

Options

  • AThe project stakeholders to communicate the delay.
  • BResource A to confirm estimates.
  • CThe other team members to make up the schedule slippage.
  • DThe manager of Resource A for corrective action.