Which of the following areas are addressed in the Project Charter?

The correct answer is C. Business needs. This question asks to identify a core element that is documented within a project charter.

Tools and documentation

Question

Which of the following areas are addressed in the Project Charter?

Options

  • AProject team members
  • BWork Breakdown Structure (WBS)
  • CBusiness needs
  • DCommunications venue

How the community answered

(31 responses)
  • A
    3% (1)
  • C
    94% (29)
  • D
    3% (1)

Why each option

This question asks to identify a core element that is documented within a project charter.

AProject team members

While key stakeholders might be identified, detailed project team members are typically identified during planning, not in the high-level charter.

BWork Breakdown Structure (WBS)

The Work Breakdown Structure (WBS) is a detailed breakdown of project scope into deliverables, created during the planning process, not in the initial charter.

CBusiness needsCorrect

The project charter formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. It includes the business needs that the project is intended to address, outlining the project's purpose and justification.

DCommunications venue

Detailed communication plans, including specific venues, are part of the project communications management plan, developed during project planning, not in the initial charter.

Concept tested: Project Charter components - Business Needs