A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a worka

The correct answer is A. Transference.. This question describes a scenario where a project manager addresses a risk by hiring an external entity to handle the problematic deliverable.

Project management concepts

Question

A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a workaround, to contract with a third party. This type of risk response is called:

Options

  • ATransference.
  • BAvoidance.
  • CMonitor and Prepare.
  • DAcceptance.

How the community answered

(69 responses)
  • A
    74% (51)
  • B
    9% (6)
  • C
    13% (9)
  • D
    4% (3)

Why each option

This question describes a scenario where a project manager addresses a risk by hiring an external entity to handle the problematic deliverable.

ATransference.Correct

Risk transference involves shifting the responsibility and impact of a risk to a third party, making them accountable for managing it. Contracting with a third party to handle a deliverable for which the internal team lacks expertise is a direct example of transferring this risk.

BAvoidance.

Avoidance would mean changing the project plan to eliminate the deliverable or the need for that specific expertise, not hiring someone else to do it.

CMonitor and Prepare.

Monitor and Prepare implies developing contingency plans or strategies to monitor the risk without shifting its ownership or impact to a third party.

DAcceptance.

Acceptance would mean acknowledging the lack of expertise and either passively accepting the consequences or actively planning for them without contracting it out.

Concept tested: Project risk response - Transference

Topics

#risk transference#risk response strategies#third-party contracts#vendor management

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice