PK0-003 · Question #127
The project manager will define a scale of probability from "unlikely" to "certain" in which of the following documents?
The correct answer is A. Risk management plan. The risk management plan is the document where the approach to managing project risks is defined, including the scales used to assess risk probability and impact.
Question
The project manager will define a scale of probability from "unlikely" to "certain" in which of the following documents?
Options
- ARisk management plan
- BScope management plan
- CQuality management plan
- DSchedule management plan
How the community answered
(28 responses)- A93% (26)
- C4% (1)
- D4% (1)
Why each option
The risk management plan is the document where the approach to managing project risks is defined, including the scales used to assess risk probability and impact.
The risk management plan is the foundational document that details how all risk management activities will be performed throughout the project lifecycle. It specifically defines the methodologies, roles, responsibilities, and the precise scales for assessing risk probability, such as "unlikely" to "certain", and their potential impact on project objectives.
The scope management plan defines how the project scope will be defined, developed, monitored, controlled, and verified, not how risks are quantified.
The quality management plan outlines how quality policies will be implemented, focusing on ensuring project and product requirements are met, not on risk probability scales.
The schedule management plan establishes the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule, not for risk assessment scales.
Concept tested: Risk management plan contents