PK0-003 · Question #118
Which of the following project documents lists risks and describes the strategy to deal with a risk?
The correct answer is B. Risk register. The Risk Register is a project document that comprehensively lists identified risks and details the planned responses or strategies for each risk. It serves as a central repository for all risk-related information throughout the project lifecycle.
Question
Which of the following project documents lists risks and describes the strategy to deal with a risk?
Options
- ARisk categorization
- BRisk register
- CRisk analysis
- DRisk breakdown structure
How the community answered
(27 responses)- A4% (1)
- B89% (24)
- D7% (2)
Why each option
The Risk Register is a project document that comprehensively lists identified risks and details the planned responses or strategies for each risk. It serves as a central repository for all risk-related information throughout the project lifecycle.
Risk categorization is the process of grouping risks by common root causes, not a document listing individual risks and their strategies.
A risk register is a detailed record of all identified risks in a project, including their description, potential impact, probability, owners, and the planned response strategies to mitigate, accept, transfer, or avoid them. It is a dynamic document updated throughout the project.
Risk analysis is the process of assessing risks (qualitative or quantitative) to understand their nature and potential impact, not a document that lists risks and their strategies.
A risk breakdown structure (RBS) is a hierarchical representation of risks organized by category, providing a framework for identifying risks, but it does not detail specific risk response strategies.
Concept tested: Project risk management documentation