PGMP · Question #570
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress?
The correct answer is C. Provide additional program performance reports to the key stakeholder.. When a stakeholder asks mid-program whether objectives are being met, the most direct and credible response is to provide program performance reports. These reports contain quantitative, objective data-milestone completions, schedule and cost performance indices, KPI status, and
Question
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress?
Options
- ADefine the key performance indicators (KPIs) for the program's outcome.
- BInvite the key stakeholder to review the program charter and the program objectives.
- CProvide additional program performance reports to the key stakeholder.
- DMaintain the benefits register and provide it to the key stakeholder.
How the community answered
(43 responses)- A14% (6)
- B2% (1)
- C79% (34)
- D5% (2)
Explanation
When a stakeholder asks mid-program whether objectives are being met, the most direct and credible response is to provide program performance reports. These reports contain quantitative, objective data-milestone completions, schedule and cost performance indices, KPI status, and deliverable progress-that directly demonstrate whether the program is on track against its defined objectives. Option A is incorrect because KPIs should already be defined, not created now. Option B shows original goals but not current progress. Option D (benefits register) tracks expected future benefits, not current performance evidence.
Topics
Community Discussion
No community discussion yet for this question.