PGMP · Question #101

A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Onc

The correct answer is A. Defect repair validation. After a defect is repaired, the next required step is defect repair validation to confirm the fix was implemented correctly and the issue is resolved.

Program Lifecycle Management

Question

A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

Options

  • ADefect repair validation
  • BLesson learned documentation
  • CCorrective actions
  • DPreventive actions

How the community answered

(31 responses)
  • A
    77% (24)
  • B
    13% (4)
  • C
    6% (2)
  • D
    3% (1)

Why each option

After a defect is repaired, the next required step is defect repair validation to confirm the fix was implemented correctly and the issue is resolved.

ADefect repair validationCorrect

Defect repair validation is the formal process of inspecting and confirming that a repaired defect has been correctly fixed. After the team member corrects the installation problem, someone must verify the repair was performed properly before work continues. This step ensures the corrected fixture meets the original acceptance criteria.

BLesson learned documentation

Lessons learned documentation is recorded at phase or project closure, not immediately after a single defect repair.

CCorrective actions

Corrective action is what the team member already performed by fixing the installation - it is the repair itself, not what follows it.

DPreventive actions

Preventive actions address future potential problems and are not the immediate next step after repairing an existing defect.

Concept tested: Defect repair validation in project quality control

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Quality Management#Defect Management#Validation#Program Control