PGMP · Question #55
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
The correct answer is D. Program charter. The program charter is the foundational document that authorizes the program, establishes its mandate, sets the overall timeline, and identifies key milestones for delivering products or incremental benefits. It gives the program manager the authority to apply organizational reso
Question
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
Options
- AProgram architecture baseline
- BProgram risk register
- CProgram WBS
- DProgram charter
How the community answered
(29 responses)- B3% (1)
- C7% (2)
- D90% (26)
Why each option
The program charter is the foundational document that authorizes the program, establishes its mandate, sets the overall timeline, and identifies key milestones for delivering products or incremental benefits. It gives the program manager the authority to apply organizational resources.
The program architecture baseline is a technical document capturing the structural design and component relationships of the program - it does not provide organizational mandate or delivery milestones.
The program risk register is a log of identified risks, their probability, impact, and response plans - it is not a mandate or milestone document.
The program work breakdown structure (WBS) decomposes the program scope into manageable components but does not provide organizational authorization or mandate.
The program charter formally authorizes the existence of the program, defines its high-level scope and objectives, identifies the sponsor, and presents the key milestones tied to benefit delivery or product increments. It provides the mandate under which the program operates and within which the program manager has authority to act. Without the charter, the program lacks formal organizational sanction and a documented delivery timeline.
Concept tested: Program charter purpose and authority
Source: https://www.pmi.org/pmbok-guide-standards/framework/standard-for-program-management
Topics
Community Discussion
No community discussion yet for this question.