PGMP · Question #55

PGMP Question #55: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #55. The question stem and answer options stay visible for context.

Program Lifecycle Management

Question

Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

Options

  • AProgram architecture baseline
  • BProgram risk register
  • CProgram WBS
  • DProgram charter

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Program Charter#Program Initiation#Program Lifecycle Management#Program Governance