You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of you

The correct answer is B. Program transition plan. The program transition plan defines how program benefits and deliverables will be transferred to ongoing operations at the conclusion of the program. It ensures a structured handoff so that benefits are sustained after the program closes.

Program Life Cycle Management

Question

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Options

  • AOperational transfer plan
  • BProgram transition plan
  • CBenefits transfer plan
  • DProgram closure plan

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    93% (43)
  • C
    4% (2)

Why each option

The program transition plan defines how program benefits and deliverables will be transferred to ongoing operations at the conclusion of the program. It ensures a structured handoff so that benefits are sustained after the program closes.

AOperational transfer plan

There is no standard PMI plan called an 'operational transfer plan' - this is a fabricated term that does not correspond to a recognized program management artifact.

BProgram transition planCorrect

The program transition plan is the specific document within program management planning that outlines how completed deliverables and realized benefits will be formally transferred from the program to the receiving operational organization. It details transition activities, responsibilities, timing, and success criteria to ensure the organization can sustain the benefits without the program team. This plan bridges the gap between program execution and long-term benefit realization.

CBenefits transfer plan

'Benefits transfer plan' is not a recognized plan name in the PMI Standard for Program Management - the correct term is program transition plan.

DProgram closure plan

The program closure plan governs how the program itself will be closed and administratively wound down, not specifically how benefits are transferred to operations.

Concept tested: Program transition plan and benefits handoff to operations

Source: https://www.pmi.org/pmbok-guide-standards/framework/standard-for-program-management

Topics

#Program Transition Plan#Program Life Cycle#Benefits Transfer#Program Management Plans