PGMP · Question #29
In which of the following processes is the program charter created?
The correct answer is C. Initiate Program. The program charter is created during the Initiate Program process, formally authorizing the program and granting the program manager authority.
Question
In which of the following processes is the program charter created?
Options
- AEstablish Program Financial Framework
- BPlan Program Scope
- CInitiate Program
- DDevelop Program Management Plan
How the community answered
(42 responses)- A2% (1)
- B2% (1)
- C88% (37)
- D7% (3)
Why each option
The program charter is created during the Initiate Program process, formally authorizing the program and granting the program manager authority.
Establish Program Financial Framework occurs after program initiation and focuses on setting up the financial governance structure, not creating the authorizing charter.
Plan Program Scope is a planning process that occurs after the program has been authorized via the charter - it defines scope boundaries, not the charter itself.
The Initiate Program process is where senior management formally authorizes the program by creating and approving the program charter. This document establishes the program's existence, defines its high-level objectives, and authorizes the program manager to begin assembling resources - it must exist before any financial framework, scope planning, or management plan development can begin.
Develop Program Management Plan is a planning process that details how the program will be executed and is created after the charter already exists.
Concept tested: Program charter creation during program initiation process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management