You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that…

The correct answer is A. Quality assurance. Quality assurance focuses on the adequacy of processes used to create deliverables, ensuring work is performed correctly from the start rather than inspecting output after the fact.

Program Life Cycle Management

Question

You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

Options

  • AQuality assurance
  • BScope verification
  • CQuality control
  • DProcess improvement

How the community answered

(48 responses)
  • A
    90% (43)
  • B
    6% (3)
  • C
    2% (1)
  • D
    2% (1)

Why each option

Quality assurance focuses on the adequacy of processes used to create deliverables, ensuring work is performed correctly from the start rather than inspecting output after the fact.

AQuality assuranceCorrect

Quality assurance (QA) is a proactive process that audits and evaluates the processes, tools, and standards being used to ensure they are appropriate and being followed correctly. The emphasis on 'doing work correctly the first time' is the hallmark of QA - it prevents defects through process adherence rather than detecting them through inspection after completion.

BScope verification

Scope verification (now called Validate Scope) is the process of formally obtaining customer acceptance of completed deliverables - it confirms scope fulfillment, not process correctness.

CQuality control

Quality control involves inspecting and measuring the outputs or deliverables after work is completed to identify defects - it is reactive, not proactive like the scenario describes.

DProcess improvement

Process improvement is a component of quality management focused on enhancing existing processes over time, but the scenario specifically describes enforcing correct execution of the current plan, which is quality assurance.

Concept tested: Quality assurance versus quality control in program management

Source: https://www.pmi.org/learning/library/quality-assurance-quality-control-8977

Topics

#Quality Assurance#Program Quality Management#Program Execution#Process Adherence