nerdexam
PMI

PGMP · Question #31

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

The correct answer is D. Configuration Management System. The Configuration Management System (CMS) is responsible for evaluating, testing, and documenting changes to the project scope - specifically managing the technical and administrative direction of a project's products and components. It identifies and documents functional and…

Program Governance

Question

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Options

  • AProject Management Information System
  • BIntegrated Change Control
  • CScope Verification
  • DConfiguration Management System

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    4% (2)
  • D
    92% (49)

Explanation

The Configuration Management System (CMS) is responsible for evaluating, testing, and documenting changes to the project scope - specifically managing the technical and administrative direction of a project's products and components. It identifies and documents functional and physical characteristics, controls changes to those characteristics, and records/reports change processing and implementation status. While Integrated Change Control (B) governs the overall change approval process, it is the CMS that handles the technical evaluation, testing, and documentation of changes. The Project Management Information System (A) is a broader toolset for collecting and distributing project information, and Scope Verification (C) is the process of formally accepting completed deliverables - neither is responsible for change evaluation and documentation.

Topics

#Configuration Management#Change Management System#Program Governance#Scope Baseline

Community Discussion

No community discussion yet for this question.

Full PGMP Practice