You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the…

The correct answer is C. Program scope statement. The program scope statement defines what is included in and excluded from the program, establishing the boundaries and deliverables. It serves as the baseline against which all future program decisions are evaluated - particularly decisions about whether something is in scope…

Program Life Cycle

Question

You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?

Options

  • AProgram budget
  • BProgram management plan
  • CProgram scope statement
  • DProgram requirements

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    89% (32)
  • D
    3% (1)

Explanation

The program scope statement defines what is included in and excluded from the program, establishing the boundaries and deliverables. It serves as the baseline against which all future program decisions are evaluated - particularly decisions about whether something is in scope or out of scope. While the program management plan is broader and guides execution, the scope statement is the foundational baseline for decisions. Budget and requirements are inputs to planning, not the decision-making baseline document.

Topics

#Program Scope Management#Program Planning#Program Documentation#Decision Making