nerdexam
PMI

PGMP · Question #278

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has…

The correct answer is B. Archive the project records. Archiving project records is a required closure activity per PMI standards. All project documentation - plans, contracts, reports, lessons learned, acceptance documents - must be archived so they are available for future reference, audits, or similar future projects. The other…

Program Life Cycle Management

Question

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Options

  • ASummarize the project variance.
  • BArchive the project records.
  • CSummarize the project risks costs.
  • DClose the project office.

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    88% (30)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Archiving project records is a required closure activity per PMI standards. All project documentation - plans, contracts, reports, lessons learned, acceptance documents - must be archived so they are available for future reference, audits, or similar future projects. The other options (summarizing variance, summarizing risk costs, closing the project office) may be components of closure activities, but archiving records is a standard, required deliverable of project closure that Marty has not yet completed.

Topics

#Project Closure#Close Project or Phase#Archiving Project Records#Program Life Cycle

Community Discussion

No community discussion yet for this question.

Full PGMP Practice