PMIPMI
PGMP · Question #115
PGMP Question #115: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #115. The question stem and answer options stay visible for context.
Program Life Cycle
Question
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
Options
- A.99
- B-$2,500
- C$2,500
- D1.02
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Earned Value Management (EVM)#Cost Variance (CV)#Program Performance Measurement#Cost Control