PGMP · Question #115
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
The correct answer is C. $2,500. Cost Variance (CV) = Earned Value (EV) − Actual Cost (AC). First, calculate EV: EV = BAC × % Complete = $550,000 × 0.25 = $137,500. Then calculate CV: CV = $137,500 − $135,000 = $2,500. A positive CV means the program is under budget. The value 0.99 and 1.02 resemble a Cost Perfo
Question
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
Options
- A.99
- B-$2,500
- C$2,500
- D1.02
How the community answered
(45 responses)- A2% (1)
- B11% (5)
- C82% (37)
- D4% (2)
Explanation
Cost Variance (CV) = Earned Value (EV) − Actual Cost (AC). First, calculate EV: EV = BAC × % Complete = $550,000 × 0.25 = $137,500. Then calculate CV: CV = $137,500 − $135,000 = $2,500. A positive CV means the program is under budget. The value 0.99 and 1.02 resemble a Cost Performance Index (CPI = EV/AC), not a variance. A negative $2,500 would indicate an over-budget condition, which is not the case here.
Topics
Community Discussion
No community discussion yet for this question.