nerdexam
PMI

PGMP · Question #114

Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their…

The correct answer is A. Alternative identification. Alternative identification is the process of identifying and evaluating different approaches or options for completing project scope. Choosing between two acceptable options - carpet or tile - during scope definition is a textbook example of this technique. Work packages are…

Program Life Cycle - Planning

Question

Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

Options

  • AAlternative identification
  • BWork packages
  • CRequirements
  • DScope decomposition

How the community answered

(29 responses)
  • A
    90% (26)
  • B
    7% (2)
  • C
    3% (1)

Explanation

Alternative identification is the process of identifying and evaluating different approaches or options for completing project scope. Choosing between two acceptable options - carpet or tile - during scope definition is a textbook example of this technique. Work packages are the lowest-level deliverables in a WBS. Requirements represent what stakeholders need the project to deliver (a step that would precede this choice). Scope decomposition is the process of breaking down high-level scope into smaller, manageable components, which is distinct from selecting between viable alternatives.

Topics

#Scope Definition#Alternatives Analysis#Project Planning#Planning Approaches

Community Discussion

No community discussion yet for this question.

Full PGMP Practice