A company hired you as a new portfolio manager, and the CEO asked you to propose a method to manage the organizational portfolio. What should you do first?

The correct answer is B. Understand who are key stakeholders. When beginning a portfolio management engagement, identifying key stakeholders is the essential first step because their needs and authority shape all subsequent planning.

Portfolio Strategic Management

Question

A company hired you as a new portfolio manager, and the CEO asked you to propose a method to manage the organizational portfolio. What should you do first?

Options

  • AAssess whether the organization is ready to change
  • BUnderstand who are key stakeholders
  • CAnalyze the gap between the current situation and the new strategic direction
  • DDefine the portfolio vision

How the community answered

(16 responses)
  • A
    13% (2)
  • B
    81% (13)
  • D
    6% (1)

Why each option

When beginning a portfolio management engagement, identifying key stakeholders is the essential first step because their needs and authority shape all subsequent planning.

AAssess whether the organization is ready to change

Assessing organizational readiness for change is important but cannot be done effectively until key stakeholders are identified, since their engagement and buy-in are central to that assessment.

BUnderstand who are key stakeholdersCorrect

Stakeholder identification must occur first because stakeholders provide the organizational context, strategic priorities, and constraints that inform every downstream activity. Without knowing who the key stakeholders are, any assessment, gap analysis, or vision definition would lack the organizational grounding and sponsorship needed to succeed.

CAnalyze the gap between the current situation and the new strategic direction

Analyzing the gap between the current situation and strategic direction requires stakeholder input and context that must be gathered before this analysis can be meaningful.

DDefine the portfolio vision

Defining the portfolio vision is a later step that depends on stakeholder alignment and organizational understanding that have not yet been established.

Concept tested: Stakeholder identification as first step in portfolio initiation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Initiation#Stakeholder Management#Strategic Alignment#Portfolio Planning