As part of the new strategic direction, the executive management has decided to create a portfolio for the development of a new product. You have been assigned as the portfolio manager. What should yo
The correct answer is D. Check existing portfolios, programs and projects. Before taking any action as a newly assigned portfolio manager, you must first understand the current state of the organization. Checking existing portfolios, programs, and projects (D) gives you a baseline - what components already exist, what strategic objectives they serve, an
Question
As part of the new strategic direction, the executive management has decided to create a portfolio for the development of a new product. You have been assigned as the portfolio manager. What should you do as a first step?
Options
- AUpdate the Strategic Plan
- BUpdate existing portfolio
- CDevelop the Strategic Plan
- DCheck existing portfolios, programs and projects
How the community answered
(66 responses)- A11% (7)
- B6% (4)
- C3% (2)
- D80% (53)
Explanation
Before taking any action as a newly assigned portfolio manager, you must first understand the current state of the organization. Checking existing portfolios, programs, and projects (D) gives you a baseline - what components already exist, what strategic objectives they serve, and where gaps or overlaps lie. Only after this assessment can you make informed decisions about updating or creating portfolios. Jumping to update or develop a strategic plan (A, C) without this baseline risks duplicating efforts or misaligning with work already underway. 'Update existing portfolio' (B) assumes one already maps to the new direction, which you cannot know without first checking.