PFMP · Question #252
PFMP Question #252: Real Exam Question with Answer & Explanation
The correct answer is C: strategic plan.. See the full explanation below for the reasoning.
Portfolio Strategic Management
Question
A portfolio manager is developing an initial list of portfolio components that need to be proposed to the governance board for approval of prioritization. An output of the process that the portfolio manager is currently performing is the portfolio:
Options
- Aroadmap.
- Bcharter.
- Cstrategic plan.
- Dinventory of work.
Topics
#Portfolio Strategic Planning#Portfolio Components#Portfolio Prioritization#Portfolio Deliverables