A portfolio manager is developing an initial list of portfolio components that need to be proposed to the governance board for approval of prioritization. An output of the process that the portfolio m
The correct answer is C. strategic plan.. The portfolio manager is performing the 'Define Portfolio' process. The portfolio strategic plan is the key output of this process - it documents the organizational strategy, goals, and the initial set of portfolio components proposed to achieve those goals. This plan is what get
Question
A portfolio manager is developing an initial list of portfolio components that need to be proposed to the governance board for approval of prioritization. An output of the process that the portfolio manager is currently performing is the portfolio:
Options
- Aroadmap.
- Bcharter.
- Cstrategic plan.
- Dinventory of work.
How the community answered
(65 responses)- A2% (1)
- B2% (1)
- C94% (61)
- D3% (2)
Explanation
The portfolio manager is performing the 'Define Portfolio' process. The portfolio strategic plan is the key output of this process - it documents the organizational strategy, goals, and the initial set of portfolio components proposed to achieve those goals. This plan is what gets presented to the governance board for prioritization approval. The portfolio roadmap (A) is a higher-level output produced later. The portfolio charter (B) authorizes the portfolio but is a separate document. The 'inventory of work' (D) is typically an input to the Define Portfolio process, not an output.