PFMP · Question #434
During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the…
The correct answer is B. PMIS, Authorization techniques. According to PMI's Standard for Portfolio Management, the 'Authorize Portfolio' process has two specific tools and techniques: (1) PMIS (Portfolio Management Information System), which supports tracking and communication of authorization decisions, and (2) Authorization…
Question
During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the following tools and techniques?
Options
- APMIS, Authorization techniques, Scenario Analysis
- BPMIS, Authorization techniques
- CAuthorization techniques, Scenario Analysis
- DPMIS, Authorization techniques, Review Meetings
How the community answered
(28 responses)- A4% (1)
- B93% (26)
- D4% (1)
Explanation
According to PMI's Standard for Portfolio Management, the 'Authorize Portfolio' process has two specific tools and techniques: (1) PMIS (Portfolio Management Information System), which supports tracking and communication of authorization decisions, and (2) Authorization Techniques, which are the formal methods used to approve, defer, or reject components. Scenario Analysis and Review Meetings are used in other portfolio processes (such as Optimize Portfolio), not in the Authorize Portfolio process specifically. This is a common exam trap - knowing the exact T&T per process is critical.