PFMP · Question #45
Which of the following is the output for "Develop Portfolio Charter"?
The correct answer is D. All of the above.. The 'Develop Portfolio Charter' process produces all three listed items - the Portfolio Charter, Portfolio Process Assets updates, and Strategic Plan Updates - as its outputs.
Question
Which of the following is the output for "Develop Portfolio Charter"?
Options
- APortfolio Charter
- BPortfolio Process Assets
- CStrategic Plan Updates
- DAll of the above.
How the community answered
(38 responses)- A3% (1)
- B3% (1)
- C5% (2)
- D89% (34)
Why each option
The 'Develop Portfolio Charter' process produces all three listed items - the Portfolio Charter, Portfolio Process Assets updates, and Strategic Plan Updates - as its outputs.
While the Portfolio Charter is indeed an output, selecting only A ignores the Portfolio Process Assets updates and Strategic Plan Updates that are also produced by this process.
Portfolio Process Assets updates are one output of this process but not the only one; choosing B alone is an incomplete answer.
Strategic Plan Updates are one output but not the only one; selecting C alone fails to account for the Portfolio Charter and Portfolio Process Assets updates.
According to the PMI Standard for Portfolio Management, the Develop Portfolio Charter process produces the Portfolio Charter as its primary output, along with updates to Portfolio Process Assets and the Strategic Plan. Because all three listed options are legitimate outputs of this process, 'All of the above' is the complete and correct answer.
Concept tested: Develop Portfolio Charter process outputs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management