PFMP · Question #35
You are planning how to communicate with stakeholders for your portfolio. Which inputs do you need? (Choose three.)
The correct answer is A. Portfolio process assets B. Portfolio roadmap D. Portfolio reports. According to the PMI Portfolio Management Standard, the 'Develop Portfolio Communication Management Plan' process uses Portfolio Process Assets (A), Portfolio Roadmap (B), and Portfolio Reports (D) as key inputs. Portfolio Process Assets provide historical communication…
Question
You are planning how to communicate with stakeholders for your portfolio. Which inputs do you need? (Choose three.)
Options
- APortfolio process assets
- BPortfolio roadmap
- COrganization environment factors
- DPortfolio reports
How the community answered
(21 responses)- A95% (20)
- C5% (1)
Explanation
According to the PMI Portfolio Management Standard, the 'Develop Portfolio Communication Management Plan' process uses Portfolio Process Assets (A), Portfolio Roadmap (B), and Portfolio Reports (D) as key inputs. Portfolio Process Assets provide historical communication templates and lessons learned. The Portfolio Roadmap shows the timeline of portfolio components, which dictates when and what to communicate. Portfolio Reports provide existing reporting structures and content. 'Organization environment factors' (C) is a distractor; the correct PMI term is 'Enterprise Environmental Factors,' and in this specific process it is not listed as a primary input.