You create a service level agreement (SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be…
The correct answer is A. 5 days. You've hit your limit · resets 4am (America/New_York)
manage entitlements and SLAs
Question
You create a service level agreement (SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be non-working days. If no action is taken, how many calendar days can pass before the SLA fails?
Options
- A5 days
- B7 days
- C9 days
- D11 days
How the community answered
(45 responses)- A76% (34)
- B13% (6)
- C7% (3)
- D4% (2)
Explanation
You've hit your limit · resets 4am (America/New_York)
Topics
#SLA calendar#non-working days#SLA failure calculation#service calendar