nerdexam
CompTIA

JK0-017 · Question #9

Which of the following activities occur during a project kick-off meeting? (Select TWO).

The correct answer is D. Reviewing the project goals and objectives E. Defining the project team roles and responsibilities. See the full explanation below for the reasoning.

Question

Which of the following activities occur during a project kick-off meeting? (Select TWO).

Options

  • AEnsuring the project meets the organization's strategic objectives
  • BSigning the project charter and statement of work
  • CSelecting the project manager and project sponsor
  • DReviewing the project goals and objectives
  • EDefining the project team roles and responsibilities

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    4% (1)
  • D
    79% (19)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice