The project manager can use the lowest level of the risk breakdown structure (RBS) to create which of the following documents?
The correct answer is B. Risk checklist. See the full explanation below for the reasoning.
Question
The project manager can use the lowest level of the risk breakdown structure (RBS) to create which of the following documents?
Options
- ARisk register
- BRisk checklist
- CProbability and impact matrix
- DRisk budget
How the community answered
(17 responses)- A18% (3)
- B71% (12)
- C6% (1)
- D6% (1)