Question

During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?

Options

  • AInform the sponsor and have the developer include it in the same task.
  • BDocument the change and determine the impact of the modification.
  • CAdd the task to the project plan and assign the task to the developer.
  • DInform the sponsor that the change is out of scope.

Unlock JK0-017 to see the answer