During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?

The correct answer is B. Document the change and determine the impact of the modification. See the full explanation below for the reasoning.

Question

During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?

Options

  • AInform the sponsor and have the developer include it in the same task.
  • BDocument the change and determine the impact of the modification.
  • CAdd the task to the project plan and assign the task to the developer.
  • DInform the sponsor that the change is out of scope.

How the community answered

(55 responses)
  • A
    7% (4)
  • B
    80% (44)
  • C
    2% (1)
  • D
    11% (6)