Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.

The correct answer is B. 5 days. See the full explanation below for the reasoning.

Question

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.

Options

  • A4 days
  • B5 days
  • C6 days
  • D8 days

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    77% (17)
  • C
    5% (1)
  • D
    14% (3)