CompTIA
JK0-017 · Question #246
Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.
The correct answer is B. 5 days. See the full explanation below for the reasoning.
Question
Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.
Options
- A4 days
- B5 days
- C6 days
- D8 days
How the community answered
(22 responses)- A5% (1)
- B77% (17)
- C5% (1)
- D14% (3)
Community Discussion
No community discussion yet for this question.