Which of the following directly utilize the WBS? (Select TWO).

The correct answer is C. Activity estimation E. Resource assignment. See the full explanation below for the reasoning.

Question

Which of the following directly utilize the WBS? (Select TWO).

Options

  • ACommunication plan
  • BMonte Carlo technique
  • CActivity estimation
  • DVariance analysis
  • EResource assignment

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    78% (21)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.