A project manager is using historical data from multiple projects to estimate activity durations. Which of the following network diagrams would BEST allow for the utilization of the information…
The correct answer is D. PERT. See the full explanation below for the reasoning.
Question
A project manager is using historical data from multiple projects to estimate activity durations. Which of the following network diagrams would BEST allow for the utilization of the information available?
Options
- ACPM
- BGERT
- CCCM
- DPERT
How the community answered
(29 responses)- A14% (4)
- B10% (3)
- C3% (1)
- D72% (21)