nerdexam
CompTIA

JK0-017 · Question #354

A project manager is using historical data from multiple projects to estimate activity durations. Which of the following network diagrams would BEST allow for the utilization of the information…

The correct answer is D. PERT. See the full explanation below for the reasoning.

Question

A project manager is using historical data from multiple projects to estimate activity durations. Which of the following network diagrams would BEST allow for the utilization of the information available?

Options

  • ACPM
  • BGERT
  • CCCM
  • DPERT

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    10% (3)
  • C
    3% (1)
  • D
    72% (21)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice