The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule…

The correct answer is B. Crashing. See the full explanation below for the reasoning.

Question

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager?

Options

  • ARescheduling
  • BCrashing
  • CRebaselining
  • DControl scope

How the community answered

(45 responses)
  • A
    16% (7)
  • B
    71% (32)
  • C
    9% (4)
  • D
    4% (2)