The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the…
The correct answer is C. Schedule variance. See the full explanation below for the reasoning.
Question
The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?
Options
- ACost performance index
- BRisk mitigation
- CSchedule variance
- DCost variance
How the community answered
(32 responses)- A3% (1)
- B13% (4)
- C78% (25)
- D6% (2)