A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This…

The correct answer is C. Causes of a specific event. See the full explanation below for the reasoning.

Question

A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on:

Options

  • APrioritizing the specific event.
  • BVariance in the process over time.
  • CCauses of a specific event.
  • DDetermining the number of events.

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    12% (5)
  • C
    81% (35)
  • D
    2% (1)