The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.

The correct answer is A. -80,000. See the full explanation below for the reasoning.

Question

The design activity of a project has the following cost attributes:

PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.

Options

  • A-80,000
  • B-70,000
  • C10,000
  • D120,000