nerdexam
CompTIA

JK0-017 · Question #104

JK0-017 Question #104: Real Exam Question with Answer & Explanation

Sign in or unlock JK0-017 to reveal the answer and full explanation for question #104. The question stem and answer options stay visible for context.

Question

The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.

Options

  • A-80,000
  • B-70,000
  • C10,000
  • D120,000

Unlock JK0-017 to see the answer

You've previewed enough free JK0-017 questions. Unlock JK0-017 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full JK0-017 Practice