The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.
The correct answer is A. -80,000. See the full explanation below for the reasoning.
Question
The design activity of a project has the following cost attributes:
PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.
Options
- A-80,000
- B-70,000
- C10,000
- D120,000
How the community answered
(38 responses)- A84% (32)
- B5% (2)
- C8% (3)
- D3% (1)