Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should…
The correct answer is B. Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks. See the full explanation below for the reasoning.
Question
Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should the project manager do to ensure stakeholder expectations are met?
Options
- AEnsure that Ann is involved during the testing phase of the project so she can call out functional
- BOrganize a walkthrough of the solution and ensure face-to-face updates occur every two weeks
- CEscalate the issue to the project steering committee that Ann is criticizing the project quality
- DOrganize a requirements workshop to capture any gaps
How the community answered
(32 responses)- A9% (3)
- B72% (23)
- C3% (1)
- D16% (5)