CompTIA
JK0-017 · Question #247
A project manager has inherited a project that is $5 million over budget. Which of the following would the project manager do to help determine the root cause of the budget overrun?
The correct answer is D. Review if the project has maintained alignment with the scope. See the full explanation below for the reasoning.
Question
A project manager has inherited a project that is $5 million over budget. Which of the following would the project manager do to help determine the root cause of the budget overrun?
Options
- AEnsure the project plan reflects all tasks were documented during planning
- BReview the change control log
- CPerform qualitative risk analysis
- DReview if the project has maintained alignment with the scope
How the community answered
(34 responses)- A3% (1)
- B9% (3)
- C3% (1)
- D85% (29)
Community Discussion
No community discussion yet for this question.