During a project, which of the following shows when risks should be reassessed?
The correct answer is C. Throughout the project lifecycle. See the full explanation below for the reasoning.
Question
During a project, which of the following shows when risks should be reassessed?
Options
- AA risk reassessment should occur at project closeout
- BRisks should be reviewed during lessons learned
- CThroughout the project lifecycle
- DWhen a risk has become an issue and has to be acted upon
How the community answered
(15 responses)- A7% (1)
- C80% (12)
- D13% (2)