nerdexam
CompTIA

JK0-017 · Question #248

During a project, which of the following shows when risks should be reassessed?

The correct answer is C. Throughout the project lifecycle. See the full explanation below for the reasoning.

Question

During a project, which of the following shows when risks should be reassessed?

Options

  • AA risk reassessment should occur at project closeout
  • BRisks should be reviewed during lessons learned
  • CThroughout the project lifecycle
  • DWhen a risk has become an issue and has to be acted upon

How the community answered

(15 responses)
  • A
    7% (1)
  • C
    80% (12)
  • D
    13% (2)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice