JK0-017 · Question #249
A project has 45 lines of communication. Which of the following shows how many stakeholders does the project have?
The correct answer is C. 10. See the full explanation below for the reasoning.
Question
A project has 45 lines of communication. Which of the following shows how many stakeholders does the project have?
Options
- A5
- B9
- C10
- D15
How the community answered
(39 responses)- A8% (3)
- B5% (2)
- C72% (28)
- D15% (6)