JK0-017 · Question #250
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or…
The correct answer is D. SPI = 1.20, ahead of schedule. See the full explanation below for the reasoning.
Question
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?
Options
- ASPI = 0.89, ahead of schedule
- BSPI = 0.90, behind schedule
- CSPI = 1.11, behind schedule
- DSPI = 1.20, ahead of schedule
How the community answered
(48 responses)- A8% (4)
- B17% (8)
- C4% (2)
- D71% (34)