A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?

Options

  • ASPI = 0.89, ahead of schedule
  • BSPI = 0.90, behind schedule
  • CSPI = 1.11, behind schedule
  • DSPI = 1.20, ahead of schedule