JK0-017 · Question #250

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or…

The correct answer is D. SPI = 1.20, ahead of schedule. See the full explanation below for the reasoning.

Question

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?

Options

  • ASPI = 0.89, ahead of schedule
  • BSPI = 0.90, behind schedule
  • CSPI = 1.11, behind schedule
  • DSPI = 1.20, ahead of schedule

How the community answered

(48 responses)
  • A
    8% (4)
  • B
    17% (8)
  • C
    4% (2)
  • D
    71% (34)