Administrative closure of a project includes which of the following activities?

The correct answer is C. Release project team members. See the full explanation below for the reasoning.

Question

Administrative closure of a project includes which of the following activities?

Options

  • AClose all contracts.
  • BCreate performance reports.
  • CRelease project team members.
  • DObtain a formal sign-off from the project team.

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    9% (3)
  • C
    71% (25)
  • D
    14% (5)